EXTENSION of DENTAS EGG CRATE FACTORY, ROMANIA
Mezana Romania has signed a contract for the extension of Dentas Romania Egg-Crete factory in Tartatesti, Romania (located at 27 km distance from the capital Bucharest).Location
Bucharest, Romania
Employer
Dentas Srl
Consultant/Project Management
Dentas Group
Constructed Area
5,500.00 sqm
Duration
12 Months
Scope Of Contractor
Design And Build
Having completed the first phase of the factory in 2005, the contract for the extension of factory was signed in December 2009. Within the scope of contract new raw material, storage, production hall and storage warehouse having a total of 5,200 sqm have been executed. The contract was design and built type and the works have started in January 2010 and completed April 2010.