Hasanbeyli 50 MW RES Project
Mezana has signed a contract for the civil works package of 50 MW Hasanbeyli RES Project in Osmaniye, Turkey.Location
Osmaniye, Turkey
Employer
Secretary of Energy
Consultant/Project Management
Secretary of Energy
Constructed Area
NA
Duration
11 Months
Scope Of Contractor
Civil Works
Within the scope of contract 20 units of wind turbines having 2.5 MW capacity would be installed. The works has started in June 2012 and has been completed May 2013.